Reserve margin calculator

The reserve margin is the capacity a power system holds above its peak demand, as a share of that peak: (capacity - peak) / peak. The capacity margin divides by capacity instead.

Data as of October 14, 2026

Capacity from
MW
MW
%

Reserve margin

15.0%

Capacity above peak, as a share of peak

Capacity margin

13.0%

Capacity above peak, as a share of capacity

Meets the 15.0% target exactly

Reserve margin: 15.0%Target: 15.0%

Method and data

Formula

Reserve margin = (C - P) / P
Capacity margin = (C - P) / C
Accredited capacity = sum of (MW_i × accreditation_i) + demand response + firm imports - firm exports
Surplus or shortfall (MW) = C - P × (1 + target)
C is capacity and P is peak demand, both in MW

Worked example

Reserve margin and capacity margin of a 115 GW system with a 100 GW peak
CaseInstalled (MW)Accredited (MW)Peak (MW)Reserve marginCapacity margin
All capacity firm (100%)115,000115,000100,00015.0%13.0%
30,000 MW of the capacity is solar at 7%115,00087,100100,000-12.9%-14.8%
ELCC class ratings for the 2027/2028 delivery year, as published by PJM
TechnologyPJM classAccreditation
Onshore windOnshore Wind41%
Offshore windOffshore Wind67%
Solar, fixed tiltFixed-Tilt Solar7%
Solar, trackingTracking Solar8%
Landfill gasLandfill Intermittent48%
Run-of-river hydroHydro Intermittent39%
Storage, 4 hours4-hr Storage58%
Storage, 6 hours6-hr Storage67%
Storage, 8 hours8-hr Storage70%
Storage, 10 hours10-hr Storage78%
NuclearNuclear95%
CoalCoal83%
Gas combined cycleGas Combined Cycle74%
Gas turbineGas Combustion Turbine61%
Gas turbine, dual fuelGas Combustion Turbine Dual Fuel77%
DieselDiesel Utility92%
SteamSteam72%
Waste to energyWaste to Energy Steam83%
Oil-fired turbineOil-Fired Combustion Turbine80%

Ratings are PJM's published figures for the 2027/2028 base residual auction. They apply to PJM's system and fleet and are examples, not values for other systems.

Assumptions

  • Peak demand is the forecast coincident peak: the highest hour of the system as a whole, not the sum of each customer's own peak.
  • Installed capacity is the sum of the resources' MW plus demand response and firm imports, less firm exports, because exports reduce the capacity left for the home system.
  • Accredited capacity weights each resource by the share of its MW that counts towards reliability. Demand response, imports and exports are counted at 100%, so enter them as the MW that count.
  • In the resource table the surplus or shortfall against the target is shown on both bases, accredited first. Compare the target with the basis it is set on.
  • The accreditation presets are one publisher's class ratings for the delivery year shown in the table, offered as examples. Other systems use other methods, and a class rating is not a forecast for a single plant.
  • No country benchmarks are shown, because published targets differ by system and by year. The calculator takes the target you enter.

PJM Interconnection ELCC Class Ratings for the 2027/2028 Base Residual Auction · Data as of October 14, 2026

Definition: Reserve Margin

Definition: Resource Adequacy

Definition: Effective Load Carrying Capability (ELCC)

Definition: Loss of Load Expectation (LOLE)

Tera Intelligence maps the plants, interconnectors and grids behind a system's capacity, so a reserve margin can be read against the assets that make it up. Explore the map

Questions

What is the difference between reserve margin and capacity margin?
Both measure the cushion of capacity above peak demand, but they divide by different things. The reserve margin divides by peak demand: (C - P) / P. The capacity margin divides by capacity: (C - P) / C. For 115,000 MW against a 100,000 MW peak, the reserve margin is 15.0% and the capacity margin is 13.0%. When the cushion is positive, the capacity margin is the smaller of the two. Check which one a target or a report uses before comparing figures.
What is a typical reserve margin target?
There is no universal figure. The planning authority of each system sets its own target, and it derives the target from a reliability standard instead of choosing a margin directly. A common standard is a loss-of-load expectation (LOLE) of 0.1 days per year, which means about one day of lost load in ten years. The reserve margin that meets such a standard depends on the system's mix of resources, its interconnections and the shape of its demand, so it differs between systems and changes from year to year. Use the target your planning authority publishes for your system and year.
Why does accredited capacity differ from installed capacity?
Installed capacity is nameplate MW. Accredited capacity counts only the share of each resource that can be relied on when the system is short, usually measured as effective load carrying capability (ELCC). That share depends on the technology and on the rest of the fleet. In PJM Interconnection's class ratings for the 2027/2028 delivery year, fixed-tilt solar counts for 7% of its installed MW, gas combined cycle for 74% and nuclear for 95%. In the worked example, replacing 30,000 MW of firm capacity with solar at 7% leaves 87,100 MW accredited and a reserve margin of -12.9%, against 15.0% on the installed basis. Other systems rate their resources differently, so enter the values your planning authority uses.
How do imports count towards the reserve margin?
A firm import counts as capacity only when a contract and transmission capacity will deliver it at the time of the peak; non-firm imports should be left out. Firm exports reduce the capacity available at home, so the calculator subtracts them. Imports raise the margin, but they also depend on the exporting system having a surplus in the same hour, so a system that relies on imports is exposed when its neighbours are short too.

Related tools:Capacity factor calculatorMW, MWh and MVA converter