LCOE calculator
The levelised cost of electricity (LCOE) is the constant price per MWh that recovers a plant's capital, operating and fuel costs over its life at a given discount rate: LCOE = (capex × CRF + fixed O&M) / (8.76 × CF) + variable O&M + fuel.
Data as of October 14, 2026
IRENA 2025
NLR ATB 2025
Ember 2025, national solar fleet (rooftop included) on reported, often DC, capacity: usually below a new utility plant's factor, so the LCOE reads high
Tera Intelligence modelling assumption
Real, after tax; edit for your financing
Advanced
+0.2 pts, Damodaran January 2026
Levelised cost of electricity
53.9USD/MWh
Real terms; the inputs mix IRENA 2025 and NLR ATB 2023 US dollars; 6.0% real discount rate
IRENA's range covers the projects commissioned in 2025, with IRENA's own financing assumptions.
| Input | -20% | +20% |
|---|---|---|
| Capacity factor | 67.4 | 44.9 |
| Capex | 45.5 | 62.3 |
| Discount rate | 48.5 | 59.7 |
| Fixed O&M | 51.5 | 56.3 |
LCOE in USD/MWh with one input changed and the others as entered. Base: 53.9 USD/MWh.
Method and data
Formula
LCOE = (capex × CRF + FOM) / (8.76 × CF) + VOM + fuel CRF = r × (1 + r)^n / ((1 + r)^n - 1) fuel = fuel price × heat rate With degradation d: LCOE = (capex + sum of (FOM + (VOM + fuel) × E_t) / (1 + r)^t) / (sum of E_t / (1 + r)^t), E_t = 8.76 × CF × (1 - d)^(t - 1) With c construction years: capex is spent in c equal parts and carried to the start of operation at r CRF is the capital recovery factor: the yearly payment that repays 1 USD of capex over n years at rate r
Worked example
| Case | Form | LCOE (USD/MWh) |
|---|---|---|
| Base case | Simple | 48.3 |
| Output falling 0.5% a year | Discounted year by year | 50.4 |
| Built over 2 years | Simple, capex carried to the start of operation | 52.5 |
| Technology | Location | Capex (USD/kW) | Fixed O&M (USD/kW-yr) | Capacity factor | Lifetime (years) | Source | Year |
|---|---|---|---|---|---|---|---|
| Utility-scale solar PV | Brazil | 672 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | China | 533 | 3.6 | - | 32 | IRENA | 2025 |
| Utility-scale solar PV | India | 545 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | United States | 1,180 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Africa | 837 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Europe | 823 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Eurasia | 998 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Oceania | 921 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Other Asia | 882 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Other North America | 887 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Other South America | 867 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Utility-scale solar PV | Central America and the Caribbean | 931 | 23.9 | - | 32 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Brazil | 1,282 | 40.7 | 50.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | China | 789 | 40.7 | 35.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | India | 1,172 | 15 | 31.0% | 30 | IRENA | 2025 |
| Onshore wind | United States | 1,668 | 40.7 | 42.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Africa | 1,550 | 40.7 | 43.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Europe | 1,725 | 40.7 | 34.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Eurasia | 1,397 | 40.7 | 36.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Oceania | 1,787 | 40.7 | 34.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Other Asia | 1,713 | 40.7 | 35.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Other North America | 1,810 | 40.7 | 39.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Onshore wind | Other South America | 1,314 | 40.7 | 37.0% | 30 | IRENA; O&M NLR ATB | 2025 |
| Offshore wind | United States reference | 6,058 | 87 | 46.4% | 27 | NLR ATB | 2025 |
| Combined-cycle gas (CCGT) | United States reference | 1,354 | 30.2 | - | 30 | NLR ATB | 2025 |
| Open-cycle gas (OCGT) | United States reference | 1,329 | 26.6 | - | 30 | NLR ATB | 2025 |
| Nuclear | United States reference | 7,871 | 143.9 | 93.0% | 60 | NLR ATB | 2025 (in service 2030) |
A dash means no published value; in the calculator, the solar PV capacity factor comes from the country's national fleet. Lifetimes are Tera Intelligence modelling assumptions. Capex, fixed and variable O&M, capacity factor and the LCOE range as published. IRENA presets are 2025 weighted averages per country or region, in 2025 US dollars; NLR ATB presets are United States values in 2023 US dollars. The solar PV capacity factor is the country's national fleet value derived from Ember.
| Location | PV p5 | PV average | PV p95 | Onshore wind p5 | Onshore wind average | Onshore wind p95 |
|---|---|---|---|---|---|---|
| Brazil | 26 | 37 | 53 | 27 | 31 | 37 |
| China | 28 | 36 | 55 | 19 | 27 | 38 |
| India | 29 | 35 | 41 | 32 | 43 | 46 |
| United States | 41 | 62 | 93 | 29 | 40 | 59 |
| Africa | 36 | 52 | 107 | 49 | 59 | 113 |
| Europe | 40 | 59 | 126 | 40 | 54 | 83 |
| Eurasia | 74 | 91 | 101 | 41 | 63 | 86 |
| Oceania | 27 | 41 | 96 | 48 | 48 | 48 |
| Other Asia | 35 | 57 | 127 | 42 | 83 | 117 |
| Other North America | 34 | 46 | 108 | 39 | 46 | 67 |
| Other South America | 31 | 61 | 147 | 34 | 51 | 101 |
| Central America and the Caribbean | 45 | 95 | 137 | - | - | - |
Assumptions
- Costs are real US dollars: 2025 dollars for the IRENA presets and 2023 dollars for the NLR ATB presets, which are not rebased. The result is a cost per MWh at the plant, before network charges.
- Capex is the overnight cost per kW of capacity. With construction years, it is spent in equal parts at the start of each year and carried to the start of operation at the discount rate.
- Output is the capacity factor times 8.76 MWh per kW a year. Degradation reduces it every year after the first, and the result is then discounted year by year.
- Fixed O&M is paid every year of the lifetime; variable O&M and fuel scale with output. Decommissioning and residual value are left out.
- A country without its own published row takes its IRENA region's values. Technologies that NLR ATB covers only for the United States use the United States values as a reference.
IRENA Renewable Power Generation Costs in 2025 · Licence: IRENA copyright: free use with acknowledgement · Data as of October 14, 2026
NLR Annual Technology Baseline 2025 · Licence: CC BY 4.0 · Data as of October 14, 2026
Aswath Damodaran, NYU Stern Country Default Spreads and Risk Premiums, January 2026 · Data as of October 14, 2026
Ember Yearly Electricity Data · Licence: CC BY 4.0 · Data as of October 14, 2026
Definition: Levelized Cost of Energy (LCOE)
Definition: Capacity Factor
Tera Intelligence maps the plants and projects these costs apply to, country by country. Explore the map
Questions
- What discount rate should I use for LCOE?
- Use the real, after-tax cost of capital of the project's financing. The calculator starts at 6.0% real, a level typical of contracted projects in low-risk markets; merchant projects and riskier markets need more. Adding the country risk premium adds Damodaran's premium for the country (January 2026): 3.2 percentage points for Brazil and 2.9 for India. The rate matters most for capital-heavy plants: at 8.0% instead of 7.0%, the worked example rises from 48.3 to 51.9 USD/MWh.
- Why does my LCOE differ from IRENA's?
- IRENA's figures are averages over the projects commissioned in 2025, weighted by capacity and computed with IRENA's own cost of capital for each country. For utility PV in Europe, IRENA's weighted average is 59 USD/MWh, and 90% of projects lie between 40 and 126. A different capacity factor, discount rate, lifetime or O&M cost moves your result away from that average. The PV preset also takes the national fleet's capacity factor on reported capacity, often DC, which is lower than a new plant's AC factor and raises the LCOE.
- Does LCOE include grid connection, curtailment or subsidies?
- The capex presets are total installed costs as IRENA and NLR define them, which include the plant's own connection to the grid but not wider network reinforcement. Curtailment is not modelled: lower the capacity factor by the share of output you expect to lose. Subsidies, tax credits, carbon prices and revenues are left out, because LCOE is a cost per MWh, not a price or a return.
- What is the difference between real and nominal LCOE?
- A real LCOE is in money of constant value and uses a real discount rate. Here the IRENA presets are in 2025 US dollars and the NLR ATB presets in 2023 US dollars, so a result that mixes them is only approximately in one money year. A nominal LCOE carries inflation in both the costs and the discount rate, so a flat nominal price per MWh is higher than the real one: later payments lose value to inflation. Rates convert with (1 + nominal) = (1 + real) × (1 + inflation), so the 6.0% real default is 8.1% nominal at 2.0% inflation. Compare real with real and nominal with nominal.
- How does the capacity factor change LCOE?
- Capital and fixed costs are spread over the energy produced, so that part of the LCOE is inversely proportional to the capacity factor. In the worked example (capex 1,000 USD/kW, fixed O&M 20 USD/kW-yr, 25 years, 7.0% real), the LCOE is 48.3 USD/MWh at 25%, 60.4 at 20% and 40.3 at 30%. Variable O&M and fuel are already per MWh and do not change. The capacity factor calculator measures a plant's factor and passes it to this calculator.